The Schedule

The preliminary design process began in 2007 and will take several years to complete. KDOT has identified the funding needed to complete final design plans for Phases 1-3 of the interchange. Construction will start with Phase 2 first and is anticipated to begin in late 2012. Public meetings will be used to keep the community up to speed over the course of the project.

K-7 and I-70

Today

Tomorrow

Together

2007

Develop the K-7 and I-70 conceptual improvement alternative.

 

 

2008

Design a second left turn lane onto southbound K-7 at the I-70/Canaan Center Drive intersection to reduce bottlenecks.

 

Public Meeting (February 26)

2009

Build a second left turn lane onto southbound K-7 at the I-70/Canaan Center Drive intersection.

Begin preliminary design of Phases 1-3 of the interchange.

Public Meeting (May 5)

2010

 

Finish preliminary design of Phases 1-3. Then begin right-of-way design of the same phases.

Public Meeting (August 25)

2011

 

Finish right-of-way design of Phases 1-3. Then begin final design for them.

Finish preliminary design plans for the remaining portions (Phases 4-10) of the ultimate interchange.

Public Meeting (Early 2011)

2011 - 2014   Finish final design of Phases 1-3 and build new bridges and roadway approaches over I-70 at both Riverview Avenue and 118th Street, and realign 122nd Street and Riverview Avenue (Phase 2).  

Click here to see what other KDOT projects have been scheduled.